List of steps
(Total number of steps: 6)
Préparation du dossier technique  (3)
Raccordement électrique  (3)

Preview & Print

Properties
 
Summary of the procedure
 

Where to go? (4)

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
Guichet Unique de l'Urbanisme - Rabat
1
Guichet Unique de l'Urbanisme - Rabat
Agence Redal (x 3)
2 3 6
Agence Redal
Électricien
4
Électricien
Site du Client / Chantier
5
Site du Client / Chantier

What you will get (2)

The objective of the procedure is to obtain those documents.
Facture Redal
3
Facture Redal
Contrat d'abonnement
6
Contrat d'abonnement

Required documents 

The documents with green band will be provided to you during the procedure.

Plans architecturaux
1
Plans architecturaux
Plan de masse
1
Plan de masse
Plan de situation
1
Plan de situation
CIN
2
CIN
Autorisation de construire
2
Autorisation de construire
Demande manuscrite
2
Demande d'abonnement et autorisation du propriétaire
2
Demande d'abonnement et autorisation du propriétaire
Plans NE VARIETUR
2
Plans NE VARIETUR
Devis des travaux Redal
3
Devis des travaux Redal
Schéma des installations du compteur
4
Schéma des installations du compteur

How much?

Free of charge

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  Min. Max.
Total time (sum): 0 d 8 d
of which:
Waiting time in queue (sum): 0mn 30mn
Attention at counter: 0mn 30mn
Waiting time until next step (sum): 0 d 8 d